This website has no political background and is not designed to criticize politics, goverments or stakeholders.

Russian gas to Europe is and has been a topic of discussion worldwide in politics and in almost all newspapers around the world.
However, this website is only interested in the challenges, the applied technology, logistics, etc.
The construction of two pipelines, each approximately 1200 kilometers, was an enormous challenge for all the people who worked on it.
www.wermac.org have summarized that project in 10 pages, and try to give you an impression of what we as people can be perform.

February 26, 2022


Nord Stream


Pre-Commissioning and Pressure Testing

ABSTRACT

As submarine gas pipelines get longer and more remote, the challenge of pre-commissioning becomes greater. No project demonstrates this better than the groundbreaking Nord Stream project comprising of 1,224 km x 48in twin gas transmission submarine pipelines running from Russia to Germany through the Baltic Sea - a delicate marine environment that needs to be protected and preserved.

In September 2011, the pre-commissioning of the Nord Stream Line 1 was completed ahead of schedule. Line 2 pre-commissioning was completed one year later.

This article presents the challenges experienced during the planning, engineering and preparation for the pre-commissioning and the relevant field experience collected during execution. It also gives a summary of the schedule and lessons learnt.

Pipeline Design, Pre-Commissioning Philosophy and Construction Concept

Nord Stream comprises two 48in subsea pipelines running from Russia to Germany through the Baltic Sea. The total length of each pipeline is 1,224 km. These are the world's longest single-section offshore pipelines.

The Nord Stream pipelines are defined as the offshore system which exports gas from Vyborg, Russia, crossing the Gulf of Finland and the Baltic Sea, to a receiving terminal in Lubmin (Greifswald), Germany. In addition to crossing Russia and Germany, the pipelines also cross the Exclusive Economic Zones (EEZ) of Finland, Sweden and Denmark. Each pipeline has a capacity of 84 million Sm3/day, with a total yearly capacity (for both pipelines) of 55 billion Sm3.


Nord Stream pipeline route Nord Stream pipeline route

The pipelines are designed with a segmented design pressure concept in accordance to the gas pressure profile along the route. The pipelines configuration is illustrated in Fig. 1 below. There are no intermediate platforms along the route.

Each of the three sections was installed with offshore subsea terminations (laydown heads) designed for both the start-up/abandonment operations and subsequent pre-commissioning activities. This was required because each of the sections had to be pressure tested separately.

Subsequently, the sections were joined by hyperbaric tie-ins at KP 297 and KP 675 thus creating a single 1,224 km pipeline.


Nord Stream pipeline segmentation

Nord Stream pipeline segmentation

Saipem was Main Contractor for pipelay and pre-commissioning works and Baker Hughes was Saipem Subcontractor for pre-commissioning works. As further described below, the design and construction concept had a significant impact on the pre-commissioning execution.


Please read the article, in the following PDF file.



Russian Landfall Facility in Portovaya

At the Russian landfall facility, in Portovaya Bay near Vyborg, the powerful Portovaya Compressor Station builds the pressure needed to transport gas through Nord Stream. It is managed and operated by Gazprom. The station enables the secure transmission of gas via Nord Stream all the way to Germany without interim compression.


Landfall Facility in Portovaya

German Lubmin Landfall Facility

The Lubmin landfall facility is the logistical link between the Nord Stream Pipeline system and the European long-distance gas network. Arriving from offshore in the Bay of Greifswald, Nord Stream's twin pipelines reach land near Lubmin's harbour area. The natural gas that is transported through Nord Stream starts its journey in Portovaya Bay, near Vyborg, Russia - some 1,224-kilometres away. When the gas reaches the landfall facility in Germany, it is cleaned of potential impurities in special filters, and heated to prevent condensation.


German Lubmin Landfall Facility

Reference(s) for the images and text, is owned by Nord Stream AG



Explore the World of Piping


© Werner Sölken 2008 -  
All rights reserved.
www.wermac.org uses Google Analytics

Privacy Policy

I must be old. I still believe in respect.